Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 4 Next »

This meeting instance was canceled due to DD illness. Written dev status summary below:

  • DD : Currently live testing alchemiscale-fah 0.1.0rc with alchemiscale 0.5.0rc using mskcc2 and dev.alchemiscale.org

    • worked through connectivity issues with @Mike Henry and @Hugo Macdermott-Opeskin

    • worked through FAH client issues on Iris with @Hugo Macdermott-Opeskin and @John Chodera

    • our work units generated by alchemiscale-fah successfully execute on FAH, but two issues we’re working through:

      • replays of ProtocolDAGs that previously failed always fail due to files being cleaned up too overzealously in shared space

        • working to rectify this in alchemiscale-fah

      • execution of FahNonEquilibriumCyclingProtocol Tasks bottlenecked by minimization being performed in the SetupUnit, which occurs on the host the compute service lives on

  • IK : Implementing user-defined policies for server-side errored Task restarts in alchemiscale

    • Testing is taking longer than expected to implement and is the main blocker to restart resolution

  • DD + IK : we’ve also started design cycles for Strategys; will present on this in an upcoming dev meeting

Participants

Goals

  • DD : alchemiscale roadmap

    • Q1 : complete “living networks” performance improvements

    • Q1 : Folding@Home compute services deployed in production

      • finish MVP, with integration test suite by 2024.03 2024.06

      • perform FAH tests with volunteers during 2024.04 2024.06 2024.07

        • public work server up by 2024.03.15 2024.06.11 2024.07.19 2024.07.31

        • confidential work server up by 2024.04.01 2024.07.01 2024.07.31 2024.08.16

    • Q2 Q3 : develop Strategy structure, initial implementations

      • aiming to begin design 6/26 7/10 7/24 sprint, followed by MVP development during July August

    • Q3 : enable automated Strategy execution by end of Q3, 2024 (2024.10.01) mid Q4, 2024 (2024.11.15)

  • DD : alchemiscale.org website proposal:

  • DD : proposal: reorganize alchemiscale project

    • migrate alchemiscale under OpenFreeEnergy Github org

    • create alchemiscale channel in OpenFE Slack

    • move working group meeting notes under OpenFE working group

  • DD : proposal: deprecate use of anaconda.org environments:

    • remove references to them in docs

    • keep instructions to users to clone repository, checkout release tag, install prod client env from there

  • alchemiscale development : new sprint spanning 8/7 - 8/19

Discussion topics

Notes


Action items

  •  

Decisions

  • No labels